Construction starts Summer 2014.

We're ready to start 3 major construction and testing phases of MiCasa. Follow along with us as we build MiCasa for the first time in London and travel with it to Paris to live in while we build another house for a family in need.

Phase 1:

Build

  • June 2014
  • June 2014
  • July 2014
  • July-August 2014

  • Complete design documents
  • Fundraising and material purchasing
  • CNC-milling of structure
  • Construction of MiCasa at Sustainability Park in London

Phase 2:

Move

Rebuild

Live

  • August 2014
  • August 2014
  • December 2014

  • Disassemble MiCasa, drive to Paris and reassemble MiCasa
  • Start of live test of MiCasa (2 occupants)
  • End of live test of MiCasa, disassemble MiCasa, return to London

Phase 3:

Move

Rebuild

Live?

  • January 2015

  • Reassemble MiCasa in London